Project Summary

The Learning Zone

 

Challenges:

This project presented incredible challenges with the site and sub-grade. Elevation, grading, and drainage were all concerns that needed to be addressed with this project in order to complete construction. Additionally, this winter project faced an incredible amount of rain days during the construction process.

 

Resolutions:

Baron Construction developed a solution to the grading challenges presented. We built a soil nail wall from the top-grade elevation and worked down from that point. We also built retaining walls and exported suitable fill to be used for adjacent roads and building pads on the site. Despite the challenging weather, this project was completed close to the original schedule.